What is true about Organizational Change management in OUM Manage?

The correct answer is A. Understanding how the clients deals with change is critical to driving user acceptance. The Organizational Change Management process starts at the strategic level with executives and then identifies the particular human and organizational challenges of the technology implementation in order to design a systematic, time-sensitive, and cost-effective approach to…

Project Execution and Control

Question

What is true about Organizational Change management in OUM Manage?

Options

  • AUnderstanding how the clients deals with change is critical to driving user acceptance.
  • BIt involves only the end-user community.
  • CIt increases the risk of organizational disruptions.
  • DNew technology will overcome people's resistance.

How the community answered

(34 responses)
  • A
    79% (27)
  • B
    6% (2)
  • C
    3% (1)
  • D
    12% (4)

Explanation

The Organizational Change Management process starts at the strategic level with executives and then identifies the particular human and organizational challenges of the technology implementation in order to design a systematic, time-sensitive, and cost-effective approach to lowering risk that is tailored to each organization's specific needs. In addition to increasing user adoption rates, carefully planning for and managing change in this way allows organizations to maintain productivity through often difficult technological transitions. This in turn enables the organization to more easily meet deadlines, realize business objectives, and maximize return on