1Z0-336 · Question #54
A forecast is frozen and the VP of Sales wants to extend the forecast freeze date. What are two consequences of this decision? (Choose two.)
The correct answer is C. Submitted forecasts remain unsubmitted. D. Any territory changes implemented after the original freeze date are now enforced. Explanation/Reference: C: If the forecast is frozen and the administrator extends the freeze date, then all submitted forecasts are unsubmitted and all the forecasts are no longer frozen. D: Territory hierarchy changes are not reflected in the forecast hierarchy for frozen…
Question
A forecast is frozen and the VP of Sales wants to extend the forecast freeze date. What are two consequences of this decision? (Choose two.)
Options
- ASales reps can create new forecast items but cannot edit the previously submitted items.
- BTerritory hierarchy cannot be changed.
- CSubmitted forecasts remain unsubmitted.
- DAny territory changes implemented after the original freeze date are now enforced.
How the community answered
(45 responses)- A4% (2)
- B13% (6)
- C82% (37)
Explanation
Explanation/Reference: C: If the forecast is frozen and the administrator extends the freeze date, then all submitted forecasts are unsubmitted and all the forecasts are no longer frozen. D: Territory hierarchy changes are not reflected in the forecast hierarchy for frozen forecasts. https://docs.oracle.com/cd/E48434_01/fusionapps.1118/e49571/F1109255AN598D6.htm