VDCD510 · Question #120
You are a VMware designer working on virtualizing a business application. The SLA specifies that the RTO requirement is 4 hours, and the RPO requirement is 9 hours. After months of successful use…
The correct answer is B. The application must be brought online and be accessible to users by 5 p.m. The recovery time objective (RTO)--also known as the return to operation--is the amount of time it takes to restore a service after a failure has taken place. The recovery point objective (RPO) is the point in time to which the system needs to be restored following a failure.
Question
You are a VMware designer working on virtualizing a business application. The SLA specifies that the RTO requirement is 4 hours, and the RPO requirement is 9 hours. After months of successful use, the system crashes at 1 p.m. To meet the project SLA, which of the following is true?
Options
- AThe application must be brought online and be accessible to users by 10 p.m.
- BThe application must be brought online and be accessible to users by 5 p.m.
How the community answered
(29 responses)- A21% (6)
- B79% (23)
Explanation
The recovery time objective (RTO)--also known as the return to operation--is the amount of time it takes to restore a service after a failure has taken place. The recovery point objective (RPO) is the point in time to which the system needs to be restored following a failure.
Topics
Community Discussion
No community discussion yet for this question.