VDCD510 · Question #119
You are a VMware architect working at a company where a business application is being rolled out. Based on conversations with the business, you establish that the RTO requirement is 2 hours, and the…
The correct answer is B. When the application is brought online, the data must be from a version as of 11 a.m. The recovery time objective (RTO)--also known as the return to operation--is the amount of time it takes to restore a service after a failure has taken place. The recovery point objective (RPO) is the point in time to which the system needs to be restored following a failure.
Question
You are a VMware architect working at a company where a business application is being rolled out. Based on conversations with the business, you establish that the RTO requirement is 2 hours, and the RPO requirement is 3 hours. Consider a situation in which the VMware platform is out of service following multiple hardware issues. The application dropped from service at 2 p.m. To meet the application business SLA, which of the following is true?
Options
- AWhen the application is brought online, the data must be from a version as of 4 p.m.
- BWhen the application is brought online, the data must be from a version as of 11 a.m.
How the community answered
(29 responses)- A17% (5)
- B83% (24)
Explanation
The recovery time objective (RTO)--also known as the return to operation--is the amount of time it takes to restore a service after a failure has taken place. The recovery point objective (RPO) is the point in time to which the system needs to be restored following a failure.