You are VMware architect working at a large enterprise where a new VMware platform is being installed. Based on conversations with the business, you establish that the RTO requirement is 8 hours…

The correct answer is A. the application must be brought online and be accessible to users by midnight. C. when the application is brought online the data must be from a version as of 3:45 p.m. The recovery time objective (RTO)--also known as the return to operation--is the amount of time it takes to restore a service after a failure has taken place. The recovery point objective (RPO) is the point in time to which the system needs to be restored following a failure.

Create a Design for vSphere 5.x Recoverability

Question

You are VMware architect working at a large enterprise where a new VMware platform is being installed. Based on conversations with the business, you establish that the RTO requirement is 8 hours, and the RPO requirement is 15 minutes. After months of successful use, the system crashes at 4 p.m. To meet the project SLA, _____________. (Choose two)

Options

  • Athe application must be brought online and be accessible to users by midnight.
  • Bthe application must be brought online and be accessible to users by 4:15 p.m.
  • Cwhen the application is brought online the data must be from a version as of 3:45 p.m.
  • Dwhen the application is brought online the data must be from a version as of 8 p.m. the night before.

How the community answered

(50 responses)
  • A
    76% (38)
  • B
    18% (9)
  • D
    6% (3)

Explanation

The recovery time objective (RTO)--also known as the return to operation--is the amount of time it takes to restore a service after a failure has taken place. The recovery point objective (RPO) is the point in time to which the system needs to be restored following a failure.

Topics

#RTO#RPO#SLA#recovery scenario