nerdexam
ExamsSK0-004Questions#16
CompTIA

SK0-004 · Question #16

SK0-004 Question #16: Real Exam Question with Answer & Explanation

The correct answer is A: Perform a test on the UPS batteries. See the full explanation below for the reasoning.

Question

A server technician in a datacenter configures a daemon to monitor the battery health in a UPS. Over a two day time period, the daemon generates a warning message. Which of the following represents the FIRST action that should be taken by the server technician?

Options

  • APerform a test on the UPS batteries
  • BImmediately replace the UPS batteries
  • CMove the servers connected to the UPS to another existing UPS
  • DImmediately replace the UPS with a new UPS

Community Discussion

No community discussion yet for this question.

Full SK0-004 Practice