nerdexam
Scaled_Agile

SAFE-SSM · Question #5

According to SAFe, which of the following types of work should fit into one Iteration for one team?

The correct answer is D. Stories. The type of work that should fit into one Iteration for one team is a Story. A Story is a short description of a small piece of functionality that provides value to the customer or stakeholder. Stories are derived from Features, which are larger units of value that typically…

Demonstrating SAFe Knowledge

Question

According to SAFe, which of the following types of work should fit into one Iteration for one team?

Options

  • AFeatures
  • BEpics
  • CTasks
  • DStories

How the community answered

(40 responses)
  • A
    3% (1)
  • B
    5% (2)
  • C
    3% (1)
  • D
    90% (36)

Explanation

The type of work that should fit into one Iteration for one team is a Story. A Story is a short description of a small piece of functionality that provides value to the customer or stakeholder. Stories are derived from Features, which are larger units of value that typically span multiple Iterations. Stories are also decomposed into Tasks, which are the specific activities that the team members perform to implement the Story. Stories are the primary backlog items that the team plans, estimates, and delivers in an Iteration. They are also the basis for defining and committing to the Iteration goals. Stories should be small enough to be completed within one Iteration, and they should meet the definition of ready and the definition of done.

Topics

#SAFe backlog hierarchy#Stories#Iteration#work item types

Community Discussion

No community discussion yet for this question.

Full SAFE-SSM Practice