SAFE-SSM · Question #15
Which of the following events aligns teams on a train?
The correct answer is C. PI Planning. PI Planning is one of the events that aligns teams on a train. PI Planning is a cadence-based event for the entire Agile Release Train (ART) that aligns teams and stakeholders to a shared mission and vision. PI Planning provides an opportunity for the ART to review the business…
Question
Which of the following events aligns teams on a train?
Options
- AArchitect Sync
- BIteration Planning
- CPI Planning
- DCoach Sync
How the community answered
(29 responses)- A3% (1)
- B7% (2)
- C86% (25)
- D3% (1)
Explanation
PI Planning is one of the events that aligns teams on a train. PI Planning is a cadence-based event for the entire Agile Release Train (ART) that aligns teams and stakeholders to a shared mission and vision. PI Planning provides an opportunity for the ART to review the business context and priorities, identify and resolve dependencies and risks, and commit to a realistic and achievable plan for the next Program Increment (PI). PI Planning is essential to SAFe: If you are not doing it, you are not doing SAFe.
Topics
Community Discussion
No community discussion yet for this question.