SAFE-SPC · Question #83

A Program Epic requires budgetary approval and a lightweight business case only if it spans multiple PIs.

The correct answer is B. False. Option B (False) is correct because in SAFe, all Program Epics require a Lean (lightweight) business case and budgetary approval - not just those that span multiple PIs. The trigger for this governance requirement is the epic's size and investment threshold, not its duration…

Lean Portfolio Management

Question

A Program Epic requires budgetary approval and a lightweight business case only if it spans multiple PIs.

Options

  • ATrue
  • BFalse

How the community answered

(19 responses)
  • A
    11% (2)
  • B
    89% (17)

Explanation

Option B (False) is correct because in SAFe, all Program Epics require a Lean (lightweight) business case and budgetary approval - not just those that span multiple PIs. The trigger for this governance requirement is the epic's size and investment threshold, not its duration across planning intervals.

Option A is wrong because it introduces a false condition (spanning multiple PIs) that doesn't exist in SAFe's definition of how Program Epics are governed. An epic contained within a single PI still demands a business case if it meets the cost/effort threshold that qualifies it as a Program Epic.

Memory tip: Tie the business case to size, not time. Ask yourself: "Is this big enough to be called a Program Epic?" If yes, it needs approval - full stop, no PI-count check required.

Topics

#Program Epics#budgetary approval#lightweight business case#Epic governance