SAFE-SPC · Question #84

Where are Capabilities managed?

The correct answer is D. In the Value Stream Kanban. Capabilities are Large Solution-level constructs managed in the Value Stream Kanban, which tracks their flow from identification through implementation across multiple ARTs. A (Portfolio Kanban) is wrong - the Portfolio Kanban manages Epics, which are the largest…

Large Solution SAFe

Question

Where are Capabilities managed?

Options

  • AIn the Portfolio Kanban.
  • BIn the Value Stream planning board.
  • CIn the ART Kanban.
  • DIn the Value Stream Kanban.

How the community answered

(23 responses)
  • A
    4% (1)
  • C
    4% (1)
  • D
    91% (21)

Explanation

Capabilities are Large Solution-level constructs managed in the Value Stream Kanban, which tracks their flow from identification through implementation across multiple ARTs.

  • A (Portfolio Kanban) is wrong - the Portfolio Kanban manages Epics, which are the largest portfolio-level work items, one level above Capabilities.
  • B (Value Stream planning board) is wrong - this is used during PI Planning events for scheduling and coordination, not for ongoing Kanban management of work items.
  • C (ART Kanban) is wrong - the ART Kanban manages Features, which are the Program-level decomposition of Capabilities.

Memory tip: Think of the hierarchy top-down - Epics → Capabilities → Features → Stories ("Every Company Finds Success"). Match each level to its Kanban: Portfolio → Epics, Value Stream → Capabilities, ART → Features. Capabilities live at the Value Stream (Large Solution) level, so they belong in the Value Stream Kanban.

Topics

#Capabilities#Value Stream Kanban#backlog management#portfolio levels