nerdexam
Scaled_Agile

SAFE-SPC · Question #29

SAFe uses Kanban to manage flow at the Portfolio Level for the following reasons EXCEPT __________.

The correct answer is E. To ensure that portfolio items are delivered to the Program or Solution Backlogs every 2 weeks. Option E is the exception because Portfolio Kanban operates on a continuous flow model, not a fixed cadence. Items move from one Kanban state to the next when they are ready - there is no 2-week delivery heartbeat at the Portfolio level (that fixed cadence belongs to Team…

Lean Portfolio Management

Question

SAFe uses Kanban to manage flow at the Portfolio Level for the following reasons EXCEPT __________.

Options

  • ATo ensure that the analysis and discovery work needed for the items are not time bound.
  • BTo ensure that there is visibility and transparency.
  • CTo capture all ideas in the funnel.
  • DTo limit the number of initiatives under consideration.
  • ETo ensure that portfolio items are delivered to the Program or Solution Backlogs every 2 weeks.

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    7% (2)
  • C
    7% (2)
  • E
    81% (22)

Explanation

Option E is the exception because Portfolio Kanban operates on a continuous flow model, not a fixed cadence. Items move from one Kanban state to the next when they are ready - there is no 2-week delivery heartbeat at the Portfolio level (that fixed cadence belongs to Team Iterations and PI events, not Portfolio Kanban).

Options A through D are all valid reasons SAFe uses Portfolio Kanban: A is correct because Portfolio-level analysis and discovery (e.g., Epic hypothesis development) is deliberately not time-boxed, unlike iterations; B is correct because the Kanban board provides a shared, visible view of all portfolio items and their states; C is correct because the Funnel state is specifically designed to capture all new ideas before any commitment; and D is correct because WIP limits at each Kanban state deliberately constrain the number of initiatives in progress, preventing overload.

Memory tip: Think "Portfolio Kanban = pull, not push." Items advance when ready (pull system), so there's no fixed 2-week push cycle. If you see any answer linking Portfolio Kanban to a time-boxed delivery schedule, that's your exception - time boxes live at the Team and Program levels, not the Portfolio.

Topics

#Portfolio Kanban#flow management#WIP limits#Portfolio Level

Community Discussion

No community discussion yet for this question.

Full SAFE-SPC Practice