nerdexam
BICSI

RCDDV15 · Question #253

Which two of the following apply during a project's close out process? (Choose two.)

The correct answer is A. Communicate discrepancies to responsible parties. E. Create schedule for completion of punch list. See the full explanation below for the reasoning.

Project Administration and Construction

Question

Which two of the following apply during a project's close out process? (Choose two.)

Options

  • ACommunicate discrepancies to responsible parties.
  • BBegin testing of installed infrastructure.
  • CEvaluate the surroundings of the project and report back to the communications distribution
  • DHire legal council for representation.
  • ECreate schedule for completion of punch list.

How the community answered

(50 responses)
  • A
    72% (36)
  • B
    10% (5)
  • C
    14% (7)
  • D
    4% (2)

Topics

#project closeout#punch list#discrepancy reporting#construction administration

Community Discussion

No community discussion yet for this question.

Full RCDDV15 Practice