RCDDV15 · Question #254

Telecommunications cabling (e.g., voice, data, video, security, audio, control) can be damaged during the construction phases of rough-in, drywall installation, and during the siding of the…

The correct answer is B. Prior to the installation of insulation and drywall D. During the trim-out stage of the cabling after painting. See the full explanation below for the reasoning.

Testing and Acceptance

Question

Telecommunications cabling (e.g., voice, data, video, security, audio, control) can be damaged during the construction phases of rough-in, drywall installation, and during the siding of the exterior. For these reasons, telecommunications cabling shall be acceptance tested. Acceptance testing includes visual examination and verification of all cabling and qualification of copper cabling for data cabling or certification of copper or optical fiber cabling for data cabling. Verification testing is generally performed in which two of the following steps? (Choose two.)

Options

  • APost the acceptance of the construction contract once the Project Manager has approved this
  • BPrior to the installation of insulation and drywall
  • CPrior to the installation of the cable tray system for spurs, points that would or could damage the
  • DDuring the trim-out stage of the cabling after painting
  • EPost the implementation of the construction

How the community answered

(42 responses)
  • A
    7% (3)
  • B
    71% (30)
  • C
    19% (8)
  • E
    2% (1)

Topics

#acceptance testing#verification testing#cabling installation#construction phases