RCDDV15 · Question #250
An ICT distribution designer working for the owner receives a submitted product that differs from the product specified in the contract documents. The original product is unavailable due to shipping…
The correct answer is C. Approve the submittal after verifying code compliance. See the full explanation below for the reasoning.
Project Administration and Construction
Question
An ICT distribution designer working for the owner receives a submitted product that differs from the product specified in the contract documents. The original product is unavailable due to shipping or manufacturing delay. Which action should the ICT distribution designer take?
Options
- AReject the submittal after verifying compliance with applicable standards.
- BApprove the submittal after asking about additional compensating warranty offerings.
- CApprove the submittal after verifying code compliance.
- DApprove the submittal after verifying all significant features of the originally specified product are
How the community answered
(43 responses)- A2% (1)
- B12% (5)
- C79% (34)
- D7% (3)
Topics
#submittal review#code compliance#product substitution#ICT distribution design