nerdexam
BICSI

RCDDV15 · Question #244

RCDDV15 Question #244: Real Exam Question with Answer & Explanation

The correct answer is B. Activity or component start and finish dates, as well as intermediate milestones. See the full explanation below for the reasoning.

Question

A program in a matrix organization includes subprojects for specific required technologies. The program manager assembles a team of project managers to lead each of the component projects. Each component protect requires unique technical skills and expertise. To ensure that there are no budget overruns, the program manager leverages the existing time reporting process. What is a critical component of the Program Schedule Management Process?

Options

  • AA list of all the projects that team members are working on
  • BActivity or component start and finish dates, as well as intermediate milestones
  • CTime management training programs for all team members, as well as the project managers
  • DSkill levels of the various project team members, as well as the project managers

Community Discussion

No community discussion yet for this question.

Full RCDDV15 Practice
A program in a matrix organization includes subprojects for... | RCDDV15 Q#244 Answer | NerdExam