nerdexam
BICSI

RCDDV15 · Question #118

In preparation for the development and submission of the program master schedule to a client, the program manager meets with (he component project manager and master program scheduler to discuss the…

The correct answer is C. Program-level activities and integrated component projects. See the full explanation below for the reasoning.

Program Schedule Management

Question

In preparation for the development and submission of the program master schedule to a client, the program manager meets with (he component project manager and master program scheduler to discuss the work breakdown structure (WBS). During the meeting, the master scheduler indicates that the master program schedule should include which of the following?

Options

  • AProgram benefits and all components protect activities
  • BComponent resources and their activity assignment/responsibility metrics
  • CProgram-level activities and integrated component projects
  • DProgram activities, component activities, and all other work

How the community answered

(21 responses)
  • A
    10% (2)
  • B
    5% (1)
  • C
    81% (17)
  • D
    5% (1)

Topics

#master schedule#WBS#program-level activities#component project integration

Community Discussion

No community discussion yet for this question.

Full RCDDV15 Practice