A program manager is responsible for constructing a USS50 million building Management suggests it will take three years to complete. The program manager can select a design-build option to optimize…

The correct answer is A. 1.25 years. See the full explanation below for the reasoning.

Program Schedule Management

Question

A program manager is responsible for constructing a USS50 million building Management suggests it will take three years to complete. The program manager can select a design-build option to optimize the construction schedule to 1.5 years. However heavy demand for steel is causing price increases and delivery delays. In this trend continues, it could take as long as 4.5 years to complete construction. You learn that a new technology can yield a definitive delivery schedule of 1.25 years What is the expected time of delivery?

Options

  • A1.25 years
  • B1.50 years
  • C1.75 years
  • D1.00 years

How the community answered

(19 responses)
  • A
    84% (16)
  • B
    5% (1)
  • C
    11% (2)

Topics

#schedule optimization#delivery estimation#design-build#technology-based scheduling

Community Discussion

No community discussion yet for this question.

Full RCDDV15 Practice