A program completes all component projects and all identified benefits are being delivered However, the program sponsor is concerned that long-term benefits may not meet organizational performance…
The correct answer is B. Benefits sustainment plan. See the full explanation below for the reasoning.
Program Benefits Management
Question
A program completes all component projects and all identified benefits are being delivered However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters. To ensure the realization of long-term benefits what should the program manager use?
Options
- ABenefits register
- BBenefits sustainment plan
- CBenefits management plan
- DBenefits transition plan
How the community answered
(57 responses)- A2% (1)
- B82% (47)
- C5% (3)
- D11% (6)
Topics
#benefits sustainment plan#long-term benefits#program closure#organizational performance