During the design phase, drawings for ICT communications spaces should be reviewed for Standards compliance and

The correct answer is C. client requirements. See the full explanation below for the reasoning.

Question

During the design phase, drawings for ICT communications spaces should be reviewed for Standards compliance and

Options

  • Acost projections.
  • BOSHA specifications
  • Cclient requirements
  • Dequipment availability

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    3% (1)
  • C
    81% (30)
  • D
    11% (4)