The correct answer is C. client requirements. See the full explanation below for the reasoning.
Question
During the design phase, drawings for ICT communications spaces should be reviewed for Standards compliance and
Options
- Acost projections.
- BOSHA specifications
- Cclient requirements
- Dequipment availability