The recommendation for installation of a cable tray system in buildings with removable ceiling tiles is that they be installed with a clearance of ______ or greater above ceiling tiles and…

The correct answer is D. 152 mm (6 in). See the full explanation below for the reasoning.

Question

The recommendation for installation of a cable tray system in buildings with removable ceiling tiles is that they be installed with a clearance of ______ or greater above ceiling tiles and supporting T-bars.

Options

  • A51 mm (2 in)
  • B77 mm (3 in)
  • C102 mm (4 in)
  • D152 mm (6 in)

How the community answered

(28 responses)
  • A
    7% (2)
  • B
    4% (1)
  • C
    14% (4)
  • D
    75% (21)