RCDD-002 · Question #311

When estimating an ICT distribution designer project timeline schedule based on the scope of work, which two scheduling methods use network diagrams to integrate logical activities and identify…

The correct answer is B. Gantt Chart D. Critical Path Method (CPM). See the full explanation below for the reasoning.

Question

When estimating an ICT distribution designer project timeline schedule based on the scope of work, which two scheduling methods use network diagrams to integrate logical activities and identify critical paths on the project? (Choose two.)

Options

  • AIf This Then That (IFTT)
  • BGantt Chart
  • CWork Breakdown Structure (WBS)
  • DCritical Path Method (CPM)
  • EProgram Evaluation Review Technique (PERT)

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    78% (21)
  • C
    15% (4)
  • E
    4% (1)

Community Discussion

No community discussion yet for this question.