BICSI
RCDD-002 · Question #30
Which two of the following items MUST be included in a detailed SoW? (Select two options.)
The correct answer is A. What type of work needs to be performed E. When the work will start. See the full explanation below for the reasoning.
Question
Which two of the following items MUST be included in a detailed SoW? (Select two options.)
Options
- AWhat type of work needs to be performed
- BA general description of work to be performed
- CWho must approve the Scope of work
- DHow the contract performance will be evaluated/judged
- EWhen the work will start
How the community answered
(43 responses)- A84% (36)
- B2% (1)
- C9% (4)
- D5% (2)
Community Discussion
No community discussion yet for this question.