Exhibit: In this future marina layout, assuming that there are fewer than 10 slips being cabled, what would be the pre-cabling guideline to follow for terminal A?

The correct answer is A. Installed one or two pair cables from the boat slips to a distribution terminal on the closest point of. See the full explanation below for the reasoning.

Question

Exhibit:

In this future marina layout, assuming that there are fewer than 10 slips being cabled, what would be the pre-cabling guideline to follow for terminal A?

Exhibit

RCDD-002 question #295 exhibit

Options

  • AInstalled one or two pair cables from the boat slips to a distribution terminal on the closest point of
  • BPlace distribution cable onto the dock and terminate in a suitable cabinet or enclosure. Install
  • CPre-cable each boat slip during construction.
  • DFor security, each install should be terminated in the patch panel/cross-connect at the

How the community answered

(41 responses)
  • A
    76% (31)
  • B
    7% (3)
  • C
    15% (6)
  • D
    2% (1)