RCDD-002 · Question #280

As a project manager, what should the FINAL task be at of the end of each project?

The correct answer is C. A lessons learned meeting. See the full explanation below for the reasoning.

Question

As a project manager, what should the FINAL task be at of the end of each project?

Options

  • AA costing and billing review
  • BDelivery of the final documentation
  • CA lessons learned meeting
  • DA sign off meeting with the owner

How the community answered

(38 responses)
  • A
    16% (6)
  • B
    3% (1)
  • C
    71% (27)
  • D
    11% (4)