An ICT distribution designer is coordinating with local agencies for an upcoming campus improvement project which could affect the design. Which two of the following listed items will MINIMIZE…
The correct answer is A. Identification and agreement of conduit pathway routes C. Identification of maintenance holes, hand holes locations. See the full explanation below for the reasoning.
Question
An ICT distribution designer is coordinating with local agencies for an upcoming campus improvement project which could affect the design. Which two of the following listed items will MINIMIZE design changes once the project begins? (Choose two.)
Options
- AIdentification and agreement of conduit pathway routes
- BHand off of documentation to project manager
- CIdentification of maintenance holes, hand holes locations
- DApproval of budget by chief financial officer (CFO)
- EApproval of permit by AHJ - local Fire Marshal
How the community answered
(60 responses)- A83% (50)
- B10% (6)
- D5% (3)
- E2% (1)