BICSI
RCDD-002 · Question #257
Placement of a buried OSP pathway in public Rights of Way may require a permit based on which of the following?
The correct answer is A. Locating of other utilities. See the full explanation below for the reasoning.
Question
Placement of a buried OSP pathway in public Rights of Way may require a permit based on which of the following?
Options
- ALocating of other utilities
- BBonding and grounding of metallic conductors
- CFees calculated on distance
- DBuilding entrance conduit plugging
How the community answered
(54 responses)- A72% (39)
- B4% (2)
- C17% (9)
- D7% (4)
Community Discussion
No community discussion yet for this question.