nerdexam
BICSI

RCDD-002 · Question #257

Placement of a buried OSP pathway in public Rights of Way may require a permit based on which of the following?

The correct answer is A. Locating of other utilities. See the full explanation below for the reasoning.

Question

Placement of a buried OSP pathway in public Rights of Way may require a permit based on which of the following?

Options

  • ALocating of other utilities
  • BBonding and grounding of metallic conductors
  • CFees calculated on distance
  • DBuilding entrance conduit plugging

How the community answered

(54 responses)
  • A
    72% (39)
  • B
    4% (2)
  • C
    17% (9)
  • D
    7% (4)

Community Discussion

No community discussion yet for this question.

Full RCDD-002 Practice