A company is evaluating the implementation of enterprise resource planning (ERP) software. The program manager performs an analysis to confirm the program's feasibility. What other important step…
The correct answer is C. Identification and documentation of the initial risks for ERP software Implementation. See the full explanation below for the reasoning.
Question
A company is evaluating the implementation of enterprise resource planning (ERP) software. The program manager performs an analysis to confirm the program's feasibility. What other important step should the program manager complete^
Options
- ADevelopment of the program's vision statement
- BReview of strategic goals against any external environmental factors
- CIdentification and documentation of the initial risks for ERP software Implementation
- DMapping of the financial benefits to the ERP software's functionality
How the community answered
(39 responses)- A3% (1)
- B13% (5)
- C77% (30)
- D8% (3)
Community Discussion