BICSI
RCDD-002 · Question #242
A new program manager joins a mufti-year program that has been underway for almost a year. During interviews, several stakeholders state that they do not understand how the program will help the…
The correct answer is C. Business case and program roadmap. See the full explanation below for the reasoning.
Question
A new program manager joins a mufti-year program that has been underway for almost a year. During interviews, several stakeholders state that they do not understand how the program will help the organization. At the next stakeholder meeting, what should the program manager present to address their concerns?
Options
- AProgram charter
- BProgram scope assessment results
- CBusiness case and program roadmap
- DExpected program benefits management plan
How the community answered
(26 responses)- A4% (1)
- B8% (2)
- C77% (20)
- D12% (3)
Community Discussion
No community discussion yet for this question.