RCDD-002 · Question #235
When should a program manager approve the closure of a component project?
The correct answer is A. When acceptance criteria of the project are met. See the full explanation below for the reasoning.
Question
When should a program manager approve the closure of a component project?
Options
- AWhen acceptance criteria of the project are met
- BWhen the project has delivered the protect benefits
- CWhen program deliverables are complete
- DWhen project deliverables are complete
How the community answered
(37 responses)- A78% (29)
- B14% (5)
- C5% (2)
- D3% (1)