A program manager is identifying and verifying risks as outlined in the risk management plan. The results will be recorded in which of the following?
The correct answer is A. Risk register. See the full explanation below for the reasoning.
Question
A program manager is identifying and verifying risks as outlined in the risk management plan. The results will be recorded in which of the following?
Options
- ARisk register
- BRisk monitoring and control
- CRisk response planning
- DRisk mitigation strategy
How the community answered
(40 responses)- A75% (30)
- B15% (6)
- C5% (2)
- D5% (2)