BICSI
RCDD-002 · Question #231
Company A acquires company B, which leads to a two-year program to integrate the processes and systems. Company B uses a different project management process, and the company's staff is unhappy…
The correct answer is D. Remind the project manager of the relevant program standards. See the full explanation below for the reasoning.
Question
Company A acquires company B, which leads to a two-year program to integrate the processes and systems. Company B uses a different project management process, and the company's staff is unhappy about the acquisition. As a result company B's project team fails to provide status and cost data in a format that conforms to the program standards. What should the program manager do first?
Options
- AInform the stakeholders of this Issue as soon as possible
- BChange the program standards, aligning them with the project standards
- CWork with the reports provided to extract the required information
- DRemind the project manager of the relevant program standards
How the community answered
(23 responses)- A13% (3)
- B4% (1)
- C9% (2)
- D74% (17)
Community Discussion
No community discussion yet for this question.