Question
A program was kicked off, but one of the key stakeholders was not present at the kick-off meeting. What should the program manager do to ensure that the key stakeholder is familiar with the program's benefits and supports the program'?
Options
- ANote stakeholder communication needs in the program charter and document their expectations
- BNote stakeholder communication needs in the communications management plan and document
- CMeet with the stakeholder to ensure stakeholder communication needs are documented in the
- DMeet with the stakeholder to ensure stakeholder communication needs are documented in the