nerdexam
BICSI

RCDD-002 · Question #219

A program was kicked off, but one of the key stakeholders was not present at the kick-off meeting. What should the program manager do to ensure that the key stakeholder is familiar with the…

The correct answer is C. Meet with the stakeholder to ensure stakeholder communication needs are documented in the. See the full explanation below for the reasoning.

Question

A program was kicked off, but one of the key stakeholders was not present at the kick-off meeting. What should the program manager do to ensure that the key stakeholder is familiar with the program's benefits and supports the program'?

Options

  • ANote stakeholder communication needs in the program charter and document their expectations
  • BNote stakeholder communication needs in the communications management plan and document
  • CMeet with the stakeholder to ensure stakeholder communication needs are documented in the
  • DMeet with the stakeholder to ensure stakeholder communication needs are documented in the

How the community answered

(30 responses)
  • A
    7% (2)
  • B
    17% (5)
  • C
    73% (22)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full RCDD-002 Practice