Question
A project is assigned to a qualified project manager by the program manager. The client rejects the project manager due to a lack of proper qualifications to manage such a project. What should the program manager do next?
Options
- AReassess the project manager's credentials
- BAssign a different project manager
- CReview the skill requirements of the project.
- DApply the competence assessment techniques to resolve the issue
How the community answered
(47 responses)- A4% (2)
- B9% (4)
- C72% (34)
- D15% (7)