nerdexam
BICSI

RCDD-002 · Question #207

A project is assigned to a qualified project manager by the program manager. The client rejects the project manager due to a lack of proper qualifications to manage such a project. What should the…

The correct answer is C. Review the skill requirements of the project. See the full explanation below for the reasoning.

Question

A project is assigned to a qualified project manager by the program manager. The client rejects the project manager due to a lack of proper qualifications to manage such a project. What should the program manager do next?

Options

  • AReassess the project manager's credentials
  • BAssign a different project manager
  • CReview the skill requirements of the project.
  • DApply the competence assessment techniques to resolve the issue

How the community answered

(47 responses)
  • A
    4% (2)
  • B
    9% (4)
  • C
    72% (34)
  • D
    15% (7)