A request for proposal (RFP) yields a bid with a better delivery schedule and a lower cost, but originates from a vendor not on the prequalified vendor list. During the final review of the RFPs the…
The correct answer is C. Advise the sponsor of a possible conflict of interest prior to awarding the bid. See the full explanation below for the reasoning.
Question
A request for proposal (RFP) yields a bid with a better delivery schedule and a lower cost, but originates from a vendor not on the prequalified vendor list. During the final review of the RFPs the program manager is informed that the new bidder is a relative of the project manager. Although the bid meets all company policies, the program manager is concerned about a conflict of interest. What should the program manager do?
Options
- ASelect the best bid from the prequalified vendor list
- BAccept the bid from the new vendor and document the decision.
- CAdvise the sponsor of a possible conflict of interest prior to awarding the bid
- DAdd the new vendor to the prequalified list and replace the project manager
How the community answered
(16 responses)- B6% (1)
- C81% (13)
- D13% (2)
Community Discussion