A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder but is unable to reach a compromise on the requirement. What…
The correct answer is C. Meet with the program sponsor to address the issue. See the full explanation below for the reasoning.
Question
A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder but is unable to reach a compromise on the requirement. What should the program manager do first?
Options
- AMeet with the program management office to update the benefits management plan
- BMeet with the organization's strategic planning committee to obtain clarification
- CMeet with the program sponsor to address the issue
- DMeet with the customer to determine if the stakeholder's requirement is valid
How the community answered
(40 responses)- A15% (6)
- B5% (2)
- C78% (31)
- D3% (1)