RCDD-002 · Question #201

A program manager is assigned to a large cross-functional program trial includes five different technologies and multiple workstreams. Some potential stakeholders have conflicting program…

The correct answer is C. Document stakeholder expectations in the program's risk register to determine their influence. See the full explanation below for the reasoning.

Question

A program manager is assigned to a large cross-functional program trial includes five different technologies and multiple workstreams. Some potential stakeholders have conflicting program expectations. What should the program manager do next/?

Options

  • AConduct interviews with key stakeholders, and document the results in the program management
  • BUpdate the stakeholder register to document stakeholders' positions relative to the program
  • CDocument stakeholder expectations in the program's risk register to determine their influence
  • DSend out satisfaction surveys and document the results in the program's stakeholder engagement

How the community answered

(45 responses)
  • A
    4% (2)
  • B
    9% (4)
  • C
    71% (32)
  • D
    16% (7)