A company is building a global monitoring network in 40 countries. The program completes the planning phase and a review is conducted of the program components' strategic alignment with the intended…

The correct answer is B. Program management information system (PMIS). See the full explanation below for the reasoning.

Question

A company is building a global monitoring network in 40 countries. The program completes the planning phase and a review is conducted of the program components' strategic alignment with the intended program and company goals. The review identifies issues that should be resolved to improve program progress. One of the issues identified is the lack of incorporation of both software and configuration management tools Which of the following must be addressed?

Options

  • AProgram performance monitoring and controlling
  • BProgram management information system (PMIS)
  • CProgram delivery management
  • DProgram roadmap

How the community answered

(51 responses)
  • A
    10% (5)
  • B
    82% (42)
  • C
    6% (3)
  • D
    2% (1)

Community Discussion

No community discussion yet for this question.