Question
A program completes all component projects and all identified benefits are being delivered However, the program sponsor is concerned that long-term benefits may not meet organizational performance parameters. To ensure the realization of long-term benefits what should the program manager use?
Options
- ABenefits register
- BBenefits sustainment plan
- CBenefits management plan
- DBenefits transition plan
How the community answered
(46 responses)- A2% (1)
- B83% (38)
- C11% (5)
- D4% (2)