nerdexam
BICSI

RCDD-002 · Question #181

A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a…

The correct answer is A. The program governance board. See the full explanation below for the reasoning.

Question

A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change. To whom should the change request be presented?

Options

  • AThe program governance board
  • BThe program customer
  • CThe program management office (PMO)
  • DThe protect governance board

How the community answered

(21 responses)
  • A
    81% (17)
  • B
    5% (1)
  • C
    10% (2)
  • D
    5% (1)

Community Discussion

No community discussion yet for this question.

Full RCDD-002 Practice