Question

A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change. To whom should the change request be presented?

Options

  • AThe program governance board
  • BThe program customer
  • CThe program management office (PMO)
  • DThe protect governance board