A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the…
The correct answer is C. Examine performance reports, audits, and inspections. See the full explanation below for the reasoning.
Question
A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk. What should the program manager do to monitor and control the supplier?
Options
- AUse expert judgment and update the program procurement plan
- BSeek stakeholder approval of program procurement management activities
- CExamine performance reports, audits, and inspections
- DReview proposal evaluation criteria, risk analyses, and mitigation strategies
How the community answered
(61 responses)- A2% (1)
- B10% (6)
- C84% (51)
- D5% (3)