A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the…

The correct answer is C. Examine performance reports, audits, and inspections. See the full explanation below for the reasoning.

Question

A program includes the development and shipping of 12 million product units over the next year. However, one program supplier has a history of overestimating its planned volume, which puts the product launch at risk. What should the program manager do to monitor and control the supplier?

Options

  • AUse expert judgment and update the program procurement plan
  • BSeek stakeholder approval of program procurement management activities
  • CExamine performance reports, audits, and inspections
  • DReview proposal evaluation criteria, risk analyses, and mitigation strategies

How the community answered

(61 responses)
  • A
    2% (1)
  • B
    10% (6)
  • C
    84% (51)
  • D
    5% (3)