An unforeseen geopolitical risk impacts a program to establish a company's operations abroad. Stakeholders now want to establish a risk response team to define a mitigation plan. Ultimately what…

The correct answer is A. Accept the risk. See the full explanation below for the reasoning.

Question

An unforeseen geopolitical risk impacts a program to establish a company's operations abroad. Stakeholders now want to establish a risk response team to define a mitigation plan. Ultimately what appeared to be a significant risk resulted in a negligible risk. What should the program manager recommend to stakeholders for future similar situations?

Options

  • AAccept the risk
  • BSeek an expert opinion
  • CEstablish an on-call risk response team
  • DReview the risk severity matrix

How the community answered

(27 responses)
  • A
    78% (21)
  • B
    7% (2)
  • C
    11% (3)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.

Full RCDD-002 Practice