An unforeseen geopolitical risk impacts a program to establish a company's operations abroad. Stakeholders now want to establish a risk response team to define a mitigation plan. Ultimately what…
The correct answer is A. Accept the risk. See the full explanation below for the reasoning.
Question
An unforeseen geopolitical risk impacts a program to establish a company's operations abroad. Stakeholders now want to establish a risk response team to define a mitigation plan. Ultimately what appeared to be a significant risk resulted in a negligible risk. What should the program manager recommend to stakeholders for future similar situations?
Options
- AAccept the risk
- BSeek an expert opinion
- CEstablish an on-call risk response team
- DReview the risk severity matrix
How the community answered
(27 responses)- A78% (21)
- B7% (2)
- C11% (3)
- D4% (1)
Community Discussion