An aircraft manufacturer is engaged by an airline to build a fleet of new airliners. The program charter has been approved but the stakeholders are concerned that the delivery method of the program…
The correct answer is A. Program work breakdown structure (PWBS) program scope statement, and benefits management. See the full explanation below for the reasoning.
Question
An aircraft manufacturer is engaged by an airline to build a fleet of new airliners. The program charter has been approved but the stakeholders are concerned that the delivery method of the program may not meet their expectations. Using the program master schedule what will the program manager incorporate to align the program with the expectations of the stakeholders?
Options
- AProgram work breakdown structure (PWBS) program scope statement, and benefits management
- BPWBS, benefits management plan, and program financial management plan
- CProgram charter PWBS, and program scope statement
- DProgram scope statement benefits management plan, and program financial management plan
How the community answered
(38 responses)- A76% (29)
- B3% (1)
- C16% (6)
- D5% (2)