A global enterprise resource planning (ERP) program's scope includes designing and building a global template. Plans include a pilot implementation project to validate the template, to be followed…

The correct answer is B. Benefits management plan. See the full explanation below for the reasoning.

Question

A global enterprise resource planning (ERP) program's scope includes designing and building a global template. Plans include a pilot implementation project to validate the template, to be followed by several rollout projects. During the build of the global template, a new government regulation mandates implementation of a goods and services tax (GST). What should the program manager update?

Options

  • AProgram communications management plan
  • BBenefits management plan
  • CStakeholder engagement plan
  • DBenefits transition plan

How the community answered

(51 responses)
  • A
    10% (5)
  • B
    82% (42)
  • C
    2% (1)
  • D
    6% (3)

Community Discussion

No community discussion yet for this question.