A company wants to perform a preliminary stakeholder analysis to assess a new program's support. What should the program manager develop'?
The correct answer is D. Stakeholder engagement plan, stakeholder register, and stakeholder map. See the full explanation below for the reasoning.
Question
A company wants to perform a preliminary stakeholder analysis to assess a new program's support. What should the program manager develop'?
Options
- AProgram communications management plan and the stakeholder charter
- BResponsible accountable consult and inform (RACI) matrix stakeholder list, and escalation
- CStakeholder strengths weaknesses, opportunities and threats (SWOT) analysis
- DStakeholder engagement plan, stakeholder register, and stakeholder map
How the community answered
(39 responses)- A3% (1)
- B8% (3)
- C10% (4)
- D79% (31)