A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this issue. What should the program manager do NEXT?

Options

  • AConsider the option to close out the key project
  • BEvaluate the program and re-baseline the objectives
  • CAssess the benefits and impact to the program.
  • DAmend the risk register with the key project changes