The program manager has a global program with live component projects. The program sponsor wants the management plans, processes/procedures and technology to be uniform across the program. The…

The correct answer is D. Present the risks and benefits of the changes to the program sponsor. See the full explanation below for the reasoning.

Question

The program manager has a global program with live component projects. The program sponsor wants the management plans, processes/procedures and technology to be uniform across the program. The requirements will create issues and result in increased costs. The program sponsor is new and has imposed these new requirements six months into a three-year program. What should the program manager do next?

Options

  • AAccept what the program sponsor requires and implement the changes
  • BDiscuss the proposed changes with the stakeholders and project managers, and give the
  • CRespond to the program sponsor if the program sponsor asks about It a second time
  • DPresent the risks and benefits of the changes to the program sponsor

How the community answered

(27 responses)
  • A
    19% (5)
  • B
    7% (2)
  • C
    4% (1)
  • D
    70% (19)