Question

During the program execution stage the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours. What should the program manager do?

Options

  • ACommunicate to the program sponsor regarding the additional estimated cost and request a
  • BDetermine which component protects have excess capacity and rebalance those resources to the
  • CRequest that the project manager make the team members work additional hours and not bill the
  • DTalk with the project manager and find ways to reduce hours in another part of the project