BICSI
RCDD-002 · Question #129
During the program execution stage the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours. What should the program manager do?
The correct answer is D. Talk with the project manager and find ways to reduce hours in another part of the project. See the full explanation below for the reasoning.
Question
During the program execution stage the component project manager responsible for testing estimates that budgeted hours may exceed 200 hours. What should the program manager do?
Options
- ACommunicate to the program sponsor regarding the additional estimated cost and request a
- BDetermine which component protects have excess capacity and rebalance those resources to the
- CRequest that the project manager make the team members work additional hours and not bill the
- DTalk with the project manager and find ways to reduce hours in another part of the project
How the community answered
(42 responses)- A2% (1)
- B5% (2)
- C10% (4)
- D83% (35)
Community Discussion