The program manager compiles a program performance report for review by the program governance board. The performance report indicates that the scope, quality and schedule objectives have been me…

The correct answer is C. Recommend cancellation of the program based on performance metrics. See the full explanation below for the reasoning.

Question

The program manager compiles a program performance report for review by the program governance board. The performance report indicates that the scope, quality and schedule objectives have been me, but costs and resource utilization are higher than expected. The program can no longer deliver the planned return-on-investment within an acceptable level and the intended benefits have not yet been realized. After further analysis of the performance indicators the program manager should do which of the following?

Options

  • AExtend the schedule to reduce costs and resource utilization
  • BExpand the scope and continue the program until return on investment objectives can be met
  • CRecommend cancellation of the program based on performance metrics
  • DTransition the existing program results to the appropriate operational area

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    81% (25)
  • D
    13% (4)