nerdexam
BICSI

RCDD-002 · Question #120

An IT-related program has a critical team in a region experiencing a crisis. Due to uncertainty about the region's changing environment a company's senior leadership asks the program manager to…

The correct answer is D. Revisit the program management plan to clearly identify how decreasing critical team. See the full explanation below for the reasoning.

Question

An IT-related program has a critical team in a region experiencing a crisis. Due to uncertainty about the region's changing environment a company's senior leadership asks the program manager to decrease dependencies on the critical team that should the program manager do to mitigate the Impacts of this request?

Options

  • AUpdate the procurement management plan, and begin the request for proposal (RFP) process to
  • BMeet with the steering committee to request assistance and influence in obtaining additional
  • CLevel resources, and empower the critical team to complete its work before regional instability
  • DRevisit the program management plan to clearly identify how decreasing critical team

How the community answered

(14 responses)
  • A
    7% (1)
  • B
    14% (2)
  • D
    79% (11)

Community Discussion

No community discussion yet for this question.

Full RCDD-002 Practice