Question
A program manager recognizes that a successful resource being used in project A could also be used in project B. What should the program manager do first to leverage the utilization of this resource?
Options
- AAssign project A's resource to project B
- BReassign the resource to project B after protect A ends
- CPrioritize the resource to optimize their use across both projects A and B
- DMitigate risk by leveraging other resources in project A